Hillsong Church
02 Arena, London
To provide and run 6 30sqm Indoor LED ROE MC-7mm screens in a back to back formation, flown above a central stage at Londons 02 Arena for four days of live shows.

Production team says:
Very professional and efficient & always fun to work alongside! Our dedicated LED supplier across all our venues & events.
How we created the set...
Due to the O2's busy schedule we had only 4 hours to build and commission 180m2 of LED screens and their operating systems before more production was built under
and around us!! Each screen was to have an independent signal and the screens were rigged on a Kinesys system as vertical movement was part of the show.
With over 800m of Socapex and 1 km of Cat 6 cable management was a major challenge! As was handling and installation of the sheer quantity of kit in such a short timeframe!
Delivering a successful project...
iMAG chose the ROE MC-7 product, because of it's light weight and fast installation system. We met the 4 hour install and commissioning deadline by detailed pre-planning and thorough briefing of the 15 person, experienced install crew!
De-rigging immediately after the last show and was completed well within the 6 hour slot. We're proud to say that with thanks to our amazing crew, it went seamlessly!
Equipment used:
- 180sqm x ROE MC-7 Screen
- 4 x E-Vision Screen Processors
- 12 x Barco Image Pro 2s Scalers
- 400 Amp Power Lock Distro
- 1000m Cat 6